Commissioned
South-East Poland
Nozdrzec
48 MW wind40 MW PV · phase 2
88 MW
Construction began Q3 2022, financed by EBRD and mBank. Wind phase commissioned; second phase (40 MW PV) planned.
Wind and PV projects at every stage — and our own ready-to-build solar platform, CERAC RE CY.
We manage projects across Poland and Greece at every development stage, and are engaging four new ready-to-build projects under our own ownership.
Construction began Q3 2022, financed by EBRD and mBank. Wind phase commissioned; second phase (40 MW PV) planned.
Last-mile development
Last-mile development
Development
Last-mile development
A dedicated holding SPV, wholly owned by CERAC Energy CY, developing and owning a solar portfolio across Greece and Poland — all four projects ready to build.
| Project | Location | Capacity | Fin. close | COD | Output / yr |
|---|---|---|---|---|---|
| G-PV1 | Central Greece | 44 MW | Dec 2024 | Aug 2025 | ~68,000 MWh |
| G-PV2 | Central Greece | 100 MW | Feb 2025 | Jan 2026 | ~165,000 MWh |
| P-PV3 | Central Poland | 35 MW | Mar 2025 | Mar 2026 | ~49,000 MWh |
| P-PV4 | Central Poland | 20 MW | Mar 2025 | Nov 2025 | ~30,000 MWh |
| Both Polish sites have optional wind extensions of 35 MW and 20 MW. | |||||